An illustrative view of a repowered wind farm in India, showing smaller legacy turbines alongside modern, large-scale units and associated power infrastructure RenewEdge Magazine
NATIONAL NEWS

CEA Sets Grid Rules for Mixed-Age Wind Farm Repowering

The procedure sets phased grid-compliance, monitoring and model-validation requirements for projects retaining old turbines while installing new units.

Editorial Team, RenewEdge

The Central Electricity Authority (CEA) has issued a Standard Operating Procedure (SOP) establishing grid-connectivity requirements for wind power projects undergoing repowering with a combination of older and replacement wind turbine generators (WTGs). The document was listed in CEA's updates on November 19, 2026, and is dated October 26, 2026. It has been formulated with reference to the CEA (Technical Standards for Connectivity to the Grid) Regulations, 2007, and subsequent amendments, alongside the Ministry of New and Renewable Energy's National Repowering and Life Extension Policy for Wind Power Projects, 2023. Its primary purpose is to establish how existing turbines and newly installed units can be assessed and monitored during phased repowering.

The procedure builds on the eligibility framework established by MNRE. Turbines may qualify for repowering or refurbishment if they do not comply with applicable quality control orders, have completed their certified design life, have a rated capacity below 2 MW, or are selected for commercial or voluntary reasons after 15 years of installation. Turbines requiring replacement because of malfunction, workmanship defects or safety concerns are also covered. The 2023 policy further defines a qualifying repowered or refurbished project by requiring annual generation to increase to at least 1.5 times the old project's actual generation, measured against its average output over the three years before disconnection. This improvement is to be achieved within three years of commissioning.

One of the SOP's important provisions concerns older turbines commissioned before the February 2019 amendment to CEA's grid-connectivity standards. These legacy WTGs, including older non-DFIG Type I and II machines, are to be grandfathered and are not required to be retrofitted to meet current standards, except where the new procedure specifically requires compliance. This is not a blanket exemption: the turbines must continue to meet the regulatory requirements applicable when they were commissioned and the requirements governing real-time power-system operation.

CEA has also specified how non-compliant legacy turbines are to be treated in steady-state grid simulation studies. Their active and reactive power injections are to be considered zero for these studies until the earliest of three events: completion of repowering, the end of the project's certified design life, or expiry of its valid power purchase agreement or energy wheeling agreement. Once any of these milestones is reached, every turbine remaining at the project, whether replaced or not, must demonstrate full compliance with the applicable CEA connectivity standards or be decommissioned or repowered. This provision is a modelling treatment for grid studies, not permission to disregard operational requirements.

The SOP addresses another practical issue by clarifying the Point of Interconnection (POI), where grid compliance is assessed. It sets out four connection configurations based on the ownership of the terminal bay and the transmission or evacuation line. Depending on the arrangement, the POI may be at the generator pooling substation, the incoming or outgoing terminal bay of a State Transmission Utility or distribution substation, or the wind project's terminal bay. For multiple turbines connected through taps on a common 22 kV or 33 kV line without a shared measurement bus, compliance is to be verified at the DISCOM or STU substation bus, the nearest feasible common measurement point.

The procedure makes monitoring equipment mandatory to assess the performance of repowered plants. A Power Quality Meter (PQM) must be installed at the terminal bay designated as the POI in all specified connection arrangements. The developer must also install a Disturbance Recorder (DR) or Digital Fault Recorder (DFR), either at the POI or at each new WTG commissioned after the February 2019 connectivity amendment. Where equipment has to be placed at a DISCOM or STU terminal bay, its installation space is to be decided in consultation with the project developer.

CEA has prescribed separate simulation requirements for assessing reactive power, power quality and dynamic performance. Developers must submit detailed Root Mean Square (RMS) models for reactive power assessment and detailed Electromagnetic Transient (EMT) models for power quality assessment. Additional aggregated RMS and EMT models are required for dynamic studies of proposed new turbine installations. The submissions must also include study reports, benchmarking and test reports, plant-level and unit-level models, and statements of compliance or conformity. New WTGs must meet applicable design-temperature requirements for delivering rated power.

The results of these studies will determine whether additional equipment is needed at the plant. CEA specifies that developers may have to install supplementary reactive power resources, harmonic filters or other mitigation devices to achieve the required performance at the POI. Such measures must be in place before physical grid interconnection. The SOP permits harmonic-filter replacement in batches, with each batch covering at least 33% of the wind project's installed capacity. Until the required compliance is achieved, the plant may schedule power injection at the POI only up to the capacity that has demonstrated compliance.

The model-validation process is also designed around phased implementation. Full validation of the plant's as-built simulation model is to be undertaken after each repowering batch reaches at least 33% of the project's installed capacity. During the interim period, developers must periodically submit PQM, DR and DFR data to the relevant transmission utility and grid operator. Partial model validation is required at successive turbine-replacement milestones, followed by complete validation after the entire repowering programme is finished.

The SOP applies to repowering projects across India covered by MNRE's 2023 policy. It also addresses partially commissioned renewable energy plants seeking to use connectivity up to the quantum already granted by the Central or State Transmission Utility, subject to consultations and confirmation of network availability and system feasibility. However, the procedure's special provisions are specific to repowering old WTGs with new ones. Where the dedicated infrastructure is shared with solar generation or battery energy storage systems, compliance must be demonstrated under the applicable CEA regulations and their existing modelling and verification requirements.  

The national scale of the opportunity is reflected in MNRE's 2023 policy, which cited a National Institute of Wind Energy estimate of 25.406 GW of repowering potential among wind turbines rated below 2 MW. Tamil Nadu accounted for the largest share at 7.3865 GW, followed by Gujarat at 4.66535 GW and Maharashtra at 3.43135 GW. These are estimates published with the 2023 policy, not current installed or confirmed repowering capacity. By clarifying how legacy and replacement turbines are assessed during the transition, the CEA procedure addresses a key technical requirement for upgrading existing wind sites while maintaining grid oversight.